2021-22 Annual Project

2021–22 Annual Plan (Excel) Analysis Report (Malayalam)

General Information

Financial Year: 2021–22

Total Projects: 172

Document Reviewed: Annual Plan (Project List)

Financial Overview

Item

Amount (₹)

Total Plan Allocation

6,05,96,489

Total Expenditure

3,06,72,082

Remaining Amount

2,99,24,407

Project Approval Status

Status

Number

Approved (Approved)

170

Send to TS Details Entry

2

Total

172

Major Projects by Sector

Sector

Number of Projects

Transportation

30

Sanitation, Waste Management

20

Drinking Water

16

Housing, House Electrification, Slum Development

15

Health

15

Analysis

A total of 172 development projects have been included in the 2021–22 financial year.

Of these, 170 projects (98.8%) have received approval. 2 projects are at the stage of entering Technical Sanction (TS) details.

Out of the total plan allocation of ₹6.06 crore, ₹3.07 crore has been spent.

Approximately 50.6% of the allocated amount has been utilized.

Approximately ₹2.99 crore is yet to be utilized.

Greater priority has been given to the sectors of transportation, sanitation, waste management, drinking water, housing development, and health.

Key Findings

The approval rate of the projects is very high.

Special importance has been given to infrastructure development, public health, and the sanitation sector.

Only about half of the allocated funds have been spent. Project implementation needs to be strengthened to utilize the remaining funds in a timely manner.

Completing the projects for which Technical Sanction has not yet been completed quickly will help improve project implementation.

Conclusion

The analysis indicates that the 2021–22 Annual Plan has formulated balanced projects covering various development sectors. Priority has been given to public-oriented sectors such as transportation, sanitation, drinking water, housing development, and health. Although the approval status of the projects is good, the Annual Plan objectives can be achieved more effectively by making financial utilization more efficient and completing the remaining projects in a timely manner.